Demand Planning > Available To Promise > Default ATP Lead Time

ATPLead Time can only be assigned on the Item record. If the ATP Lead Time isnull, NetSuite uses ninety (90) days when you check the item availability ofthe Item with null ATP Lead Time.


To illustrate:
- Create an Inventory Item with ATP Lead Time set to null.
- To make the illustration easier, make sure that the Quantity on Hand is zero(0).
- Go to Transactions > Inventory > Check Item Availability and select theItem with null ATP Lead Time created above.
- On the Quantity field, put any number that is greater than zero (0).
- On the Earliest Available Date, you will notice that it would show the date90 days after the date today.